RDS Nearing completion of M&S Welham Green Distribution Centre refurbishment.

Since the middle of September 2018 our installation teams have been hard at work conducting and now concluding the installation of 48No new RDS-ISO-40 vertical lift sectional doors, installation and refurbishment of all new dock levellers and dock shelters across the new Marks & Spencer distribution Centre in Welham Green, London.

The installation is on track to be completed well within the agreed 10 week schedule with delivery and hand over of loading bays due in the coming days.

Our Installation teams have yet again gone above and beyond to ensure the installation stayed on course without compromising quality, all product has been installed to the very highest of standards and the customer couldn’t be happier with the results.

The client is now gearing up ready to commence operations early in 2019.

Conor Rowland, RDS UK Sales Director had this to say about the success of the project “Bringing this stage of the project to a close is a great achievement by both our engineering teams who have spent the last few weeks onsite installing and also to the RDS management team who have delivered on all set deadlines. Also a special thank you to our key suppliers and trade partners who have also given everything to deliver on schedule.”

“The products we have installed and the refurbishment works have now given our client the perfect platform to commence operations from early 2019. Another week or so should see us completing phase 1 with phase 2 ready to go live in a matter of weeks. Our customer has heaped praise on the RDS team throughout the project, right back from the early stages of planning right up to closing of the last loading bay door and hand over. This particular project will be a real in Jewel in the RDS crown when complete, well done to all involved”.